Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID14hMdcRy2E2R/+EC+5TmwQ
Unique ID171318
Activity NamePersonnel Camp Accomodation
Added Dateأغسطس 4, 2009, 8:36 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37410
Total Float176,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1256,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateسبتمبر 11, 2009, 2:56 م
Planned Startمارس 10, 2010, 8 ص
Actual StartNone
Activity IDCCK00TF030
Early Startمارس 10, 2010, 8 ص
Late Startإبريل 5, 2010, 8 ص
Remaining Early Finishسبتمبر 8, 2010, 4 م
Remaining Early Startمارس 10, 2010, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 8, 2010, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 8, 2010, 4 م 
Late Finishأكتوبر 4, 2010, 4 م 
Remaining Late Finishأكتوبر 4, 2010, 4 م 
Remaining Late Startإبريل 5, 2010, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1256,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1713310,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
174979832,0 PR_SS
إلى