Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDizvcUX/xoES6hjEqzd6pZg
Unique ID172553
Activity NameEarthing & Lightening Protn: Issue PO to Vendor
Added Dateأغسطس 4, 2009, 8:36 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37488
Total Float216,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration40,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateسبتمبر 11, 2009, 2:56 م
Planned Startيناير 13, 2011, 8 ص
Actual StartNone
Activity IDHPP03EL120
Early Startيناير 13, 2011, 8 ص
Late Startفبراير 21, 2011, 8 ص
Remaining Early Finishيناير 19, 2011, 4 م
Remaining Early Startيناير 13, 2011, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDsgT5v/cSbkCCDQUP7S75Tg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيناير 19, 2011, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيناير 19, 2011, 4 م 
Late Finishفبراير 25, 2011, 4 م 
Remaining Late Finishفبراير 25, 2011, 4 م 
Remaining Late Startفبراير 21, 2011, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
40,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725520,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728570,0 PR_FS
إلى