Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID+owSaqKs00ekE3QRfOzg0w
Unique ID172594
Activity NameFireproofing Materials: Company Approval
Added Dateأغسطس 4, 2009, 8:36 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37495
Total Float477,333333
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration120,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 3, 2009, 8:53 ص
Planned Startديسمبر 6, 2010, 3:30 م
Actual StartNone
Activity IDHPP03FS020
Early Startديسمبر 6, 2010, 3:30 م
Late Startفبراير 28, 2011, 12:50 م
Remaining Early Finishديسمبر 27, 2010, 3:30 م
Remaining Early Startديسمبر 6, 2010, 3:30 م
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDmRarQ038Q02WZLZPqHT7nw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishديسمبر 27, 2010, 3:30 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishديسمبر 27, 2010, 3:30 م 
Late Finishمارس 21, 2011, 12:50 م 
Remaining Late Finishمارس 21, 2011, 12:50 م 
Remaining Late Startفبراير 28, 2011, 12:50 م 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
120,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725930,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1725950,0 PR_FS