Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDoTRUmVCkx06nbPsjBWYk6Q
Unique ID173794
Activity NameTank Painting / Lining Works
Added Dateأغسطس 7, 2009, 9:45 ص
Added Byadmin
Activity StatusTK_NotStart
WBS38591
Total Float504,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration576,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startيوليو 4, 2012, 8 ص
Actual StartNone
Activity IDCCF22PI010
Early Startيوليو 4, 2012, 8 ص
Late Startسبتمبر 16, 2012, 8 ص
Remaining Early Finishسبتمبر 25, 2012, 4 م
Remaining Early Startيوليو 4, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDwmG+yWhCcU2bG4JWSkyZKg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 25, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 25, 2012, 4 م 
Late Finishديسمبر 8, 2012, 4 م 
Remaining Late Finishديسمبر 8, 2012, 4 م 
Remaining Late Startسبتمبر 16, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
576,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1737890,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1737960,0 PR_FS