Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDBnfQY377lU+esC1hVzYuOQ
Unique ID173987
Activity NameTank Cleaning & Boxing-up
Added Dateأغسطس 10, 2009, 9:29 ص
Added Byadmin
Activity StatusTK_NotStart
WBS38680
Total Float0,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateنوفمبر 3, 2009, 10:04 ص
Planned Startديسمبر 23, 2012, 8 ص
Actual StartNone
Activity IDCCF25PC010
Early Startديسمبر 23, 2012, 8 ص
Late Startديسمبر 23, 2012, 8 ص
Remaining Early Finishديسمبر 30, 2012, 4 م
Remaining Early Startديسمبر 23, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDZTf6upRuzEmfuMSrIYBCKw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishديسمبر 30, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishديسمبر 30, 2012, 4 م 
Late Finishديسمبر 30, 2012, 4 م 
Remaining Late Finishديسمبر 30, 2012, 4 م 
Remaining Late Startديسمبر 23, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathY 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1739860,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728860,0 PR_FS
1752530,0 PR_FS