Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDcw3m5ZsE5UuDv602Ofk6HA
Unique ID174308
Activity NameTank Hydrotest
Added Dateأغسطس 11, 2009, 9:17 ص
Added Byadmin
Activity StatusTK_NotStart
WBS38928
Total Float384,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startيونيو 23, 2012, 8 ص
Actual StartNone
Activity IDCCF58TK020
Early Startيونيو 23, 2012, 8 ص
Late Startأغسطس 18, 2012, 8 ص
Remaining Early Finishيونيو 30, 2012, 4 م
Remaining Early Startيونيو 23, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID8uF6jcmdq0axGrv0ghF1kA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishيونيو 30, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishيونيو 30, 2012, 4 م 
Late Finishأغسطس 25, 2012, 4 م 
Remaining Late Finishأغسطس 25, 2012, 4 م 
Remaining Late Startأغسطس 18, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1743120,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1743100,0 PR_FS
1743130,0 PR_FS