Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDJ2jX6qK1Zkebu6bWzzvyZA
Unique ID174337
Activity NameTank Hydrotest
Added Dateأغسطس 11, 2009, 9:52 ص
Added Byadmin
Activity StatusTK_NotStart
WBS38947
Total Float140,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration205,333333
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startأغسطس 2, 2011, ظهراً
Actual StartNone
Activity IDCCD07TK030
Early Startأغسطس 2, 2011, ظهراً
Late Startأغسطس 23, 2011, 8 ص
Remaining Early Finishسبتمبر 1, 2011, 9:20 ص
Remaining Early Startأغسطس 2, 2011, ظهراً
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDXCPGpa13DUefWQVw1AY8Xw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishسبتمبر 1, 2011, 9:20 ص 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishسبتمبر 1, 2011, 9:20 ص 
Late Finishسبتمبر 21, 2011, 1:20 م 
Remaining Late Finishسبتمبر 21, 2011, 1:20 م 
Remaining Late Startأغسطس 23, 2011, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
205,333333 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1747790,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1743410,0 PR_FS
1750500,0 PR_FS