Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDBiElGawzG0yu2wOTz/+B+w
Unique ID174671
Activity NameTank Plates - Crude Oil: Issue PO
Added Dateأغسطس 25, 2009, 9:19 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37496
Total Float273,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startمايو 10, 2010, 8 ص
Actual StartNone
Activity IDHPP02TO050
Early Startمايو 10, 2010, 8 ص
Late Startيونيو 19, 2010, 9 ص
Remaining Early Finishمايو 17, 2010, 4 م
Remaining Early Startمايو 10, 2010, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishمايو 17, 2010, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishمايو 17, 2010, 4 م 
Late Finishيونيو 27, 2010, 9 ص 
Remaining Late Finishيونيو 27, 2010, 9 ص 
Remaining Late Startيونيو 19, 2010, 9 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1746700,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1746720,0 PR_SS
1728410,0 PR_FS
إلى