Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDsLOrao6kX0u0nLB35pZviA
Unique ID175106
Activity NameCathodic Protection: Final Delivery at Site
Added Dateسبتمبر 7, 2009, 9:05 ص
Added Byadmin
Activity StatusTK_NotStart
WBS37390
Total Float400,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration240,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startمارس 27, 2011, 8 ص
Actual StartNone
Activity IDMKP01EE090
Early Startمارس 27, 2011, 8 ص
Late Startمايو 24, 2011, 8 ص
Remaining Early Finishإبريل 30, 2011, 4 م
Remaining Early Startمارس 27, 2011, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDMNPyqbLxkUa7T9LufCEZnA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishإبريل 30, 2011, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishإبريل 30, 2011, 4 م 
Late Finishيونيو 27, 2011, 4 م 
Remaining Late Finishيونيو 27, 2011, 4 م 
Remaining Late Startمايو 24, 2011, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
240,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1728310,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1751050,0 PR_FS
1751350,0 PR_FS