Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDD/vPNIwiDE+2Bvieox3aaw
Unique ID175113
Activity NamePiping Hydrotest
Added Dateسبتمبر 7, 2009, 9:38 ص
Added Byadmin
Activity StatusTK_NotStart
WBS39083
Total Float16,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1672,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Dateأكتوبر 30, 2009, 3:31 م
Planned Startإبريل 1, 2012, 8 ص
Actual StartNone
Activity IDCCA02PP030
Early Startإبريل 1, 2012, 8 ص
Late Startإبريل 3, 2012, 8 ص
Remaining Early Finishنوفمبر 29, 2012, 4 م
Remaining Early Startإبريل 1, 2012, 8 ص
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID6TCxbZ2H/USuAaOU1jFjww
Lock RemainingN
4
Last Modified Byadmin 
Planned Finishنوفمبر 29, 2012, 4 م 
Actual FinishNone 
Activity TypeTT_Task 
Early Finishنوفمبر 29, 2012, 4 م 
Late Finishديسمبر 2, 2012, 4 م 
Remaining Late Finishديسمبر 2, 2012, 4 م 
Remaining Late Startإبريل 3, 2012, 8 ص 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1672,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1751312504,0 PR_SS
1751160,0 PR_FF
1751320,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
175125840,0 PR_SS
1751330,0 PR_SS
إلى