Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDrRGWtyW0skSDLoGekBkq/A
Unique ID173552
Activity NameInstru. Cable Laying
Added DateAug. 6, 2009, 9:23 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38500
Total Float16.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration2016.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJan. 1, 2012, 8 a.m.
Actual StartNone
Activity IDCCA01IC030
Early StartJan. 1, 2012, 8 a.m.
Late StartJan. 3, 2012, 8 a.m.
Remaining Early FinishOct. 20, 2012, 4 p.m.
Remaining Early StartJan. 1, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishOct. 20, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishOct. 20, 2012, 4 p.m. 
Late FinishOct. 22, 2012, 4 p.m. 
Remaining Late FinishOct. 22, 2012, 4 p.m. 
Remaining Late StartJan. 3, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
2016.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
173550416.0 PR_SS
1746400.0 PR_FS
172794960.0 PR_FF
1744970.0 PR_FS
1745010.0 PR_FS
1745050.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1735641048.0 PR_SS
Back