Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDWwZTaqvCNkCgwIBEn2lRow
Unique ID174706
Activity NamePump Columns and Internal Piping
Added DateAug. 25, 2009, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS39016
Total Float144.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration208.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartMay 21, 2012, 8 a.m.
Actual StartNone
Activity IDCCF66ME010
Early StartMay 21, 2012, 8 a.m.
Late StartJune 11, 2012, 8 a.m.
Remaining Early FinishJune 19, 2012, 4 p.m.
Remaining Early StartMay 21, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDv8LdZJAqGEGeUrrNtG/msg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 19, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 19, 2012, 4 p.m. 
Late FinishJuly 10, 2012, 4 p.m. 
Remaining Late FinishJuly 10, 2012, 4 p.m. 
Remaining Late StartJune 11, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
208.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
17470372.0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
174705160.0 PR_FS
Back