Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDQUCY8FAnRU+XrD23u8ic6g
Unique ID171374
Activity NameEquipment Data Sheets & Req.
Added DateAug. 4, 2009, 8:36 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37413
Total Float573.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1040.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateSept. 11, 2009, 2:56 p.m.
Planned StartApril 2, 2010, 8 a.m.
Actual StartNone
Activity IDHEK00EA030
Early StartApril 2, 2010, 8 a.m.
Late StartJuly 12, 2010, 1 p.m.
Remaining Early FinishSept. 30, 2010, 4 p.m.
Remaining Early StartApril 2, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 30, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 30, 2010, 4 p.m. 
Late FinishJan. 10, 2011, 1 p.m. 
Remaining Late FinishJan. 10, 2011, 1 p.m. 
Remaining Late StartJuly 12, 2010, 1 p.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float344.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1040.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1711870.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1750240.0 PR_FS