Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDgEXKIibtx0K/zGnXSIb18Q
Unique ID172534
Activity NameConcrete Piles: Company Approval
Added DateAug. 4, 2009, 8:36 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37486
Total Float176.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration120.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartJuly 7, 2010, 8 a.m.
Actual StartNone
Activity IDHPP03CV060
Early StartJuly 7, 2010, 8 a.m.
Late StartAug. 6, 2010, 8 a.m.
Remaining Early FinishJuly 27, 2010, 4 p.m.
Remaining Early StartJuly 7, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDQf5kXYtbukuuGJHYjFdN7w
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 27, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 27, 2010, 4 p.m. 
Late FinishAug. 26, 2010, 4 p.m. 
Remaining Late FinishAug. 26, 2010, 4 p.m. 
Remaining Late StartAug. 6, 2010, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
120.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725330.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1725350.0 PR_FS