Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDHgQc0rxkckKlNg/dk2Z7ZA
Unique ID173207
Activity NameIn-tank Equipment Erection
Added DateAug. 4, 2009, 11:30 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38377
Total Float360.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration496.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartApril 2, 2012, 8 a.m.
Actual StartNone
Activity IDCCF51ME010
Early StartApril 2, 2012, 8 a.m.
Late StartMay 24, 2012, 8 a.m.
Remaining Early FinishJune 12, 2012, 4 p.m.
Remaining Early StartApril 2, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID89v3H66KX0+9ysgiOuYv8A
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 12, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 12, 2012, 4 p.m. 
Late FinishAug. 4, 2012, 4 p.m. 
Remaining Late FinishAug. 4, 2012, 4 p.m. 
Remaining Late StartMay 24, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float136.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
496.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1732151248.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1732030.0 PR_FS