Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDjkXudlGpakubmM+exXzGlA
Unique ID173561
Activity NameDraingae/Sewer/Roads/Paving works
Added DateAug. 6, 2009, 9:28 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38495
Total Float472.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1672.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateSept. 11, 2009, 2:56 p.m.
Planned StartMarch 1, 2012, 8 a.m.
Actual StartNone
Activity IDCCA01CV060
Early StartMarch 1, 2012, 8 a.m.
Late StartMay 9, 2012, 8 a.m.
Remaining Early FinishOct. 30, 2012, 4 p.m.
Remaining Early StartMarch 1, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishOct. 30, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishOct. 30, 2012, 4 p.m. 
Late FinishJan. 7, 2013, 4 p.m. 
Remaining Late FinishJan. 7, 2013, 4 p.m. 
Remaining Late StartMay 9, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1672.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1713712880.0 PR_FS
1727783040.0 PR_FS
1735390.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1712980.0 PR_FS
1752590.0 PR_FS
Back