Activity NameTank Hydrotest
Added DateAug. 11, 2009, 9:07 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS38919
Total Float472.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration40.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartApril 2, 2012, 8 a.m.
Actual StartNone
Activity IDCCF38TK020
Early StartApril 2, 2012, 8 a.m.
Late StartJune 10, 2012, 8 a.m.
Remaining Early FinishApril 7, 2012, 4 p.m.
Remaining Early StartApril 2, 2012, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDF0fm+dJ5BEmSJI7tZdOgDA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishApril 7, 2012, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishApril 7, 2012, 4 p.m. 
Late FinishJune 14, 2012, 4 p.m. 
Remaining Late FinishJune 14, 2012, 4 p.m. 
Remaining Late StartJune 10, 2012, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
40.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1742990.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1742970.0 PR_FS