Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDOmUfvxVlikKejrnyuTzZ1A
Unique ID174465
Activity NameTranformer,SWGR,MCC,UPS etc.Eqp-Req.
Added DateAug. 12, 2009, 2:40 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37420
Total Float760.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration176.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 3, 2009, 9:14 a.m.
Planned StartApril 27, 2010, 8 a.m.
Actual StartNone
Activity IDHEK00EE170
Early StartApril 27, 2010, 8 a.m.
Late StartSept. 7, 2010, 8 a.m.
Remaining Early FinishMay 26, 2010, 4 p.m.
Remaining Early StartApril 27, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDIOP09ZkfhUWyGWL36difJw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMay 26, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMay 26, 2010, 4 p.m. 
Late FinishOct. 6, 2010, 4 p.m. 
Remaining Late FinishOct. 6, 2010, 4 p.m. 
Remaining Late StartSept. 7, 2010, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
176.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1744520.0 PR_FS
1744640.0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
1725960.0 PR_FS
1725540.0 PR_FS
1725990.0 PR_FS
1726020.0 PR_FS
Back