Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDiDzhg1+XiU+jZBIO0gDqJg
Unique ID174508
Activity NameInstrument Cable- Req
Added DateAug. 13, 2009, 10:48 a.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37446
Total Float228.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration352.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateOct. 30, 2009, 3:31 p.m.
Planned StartOct. 5, 2010, 8 a.m.
Actual StartNone
Activity IDHEK00IC160
Early StartOct. 5, 2010, 8 a.m.
Late StartNov. 12, 2010, noon
Remaining Early FinishDec. 3, 2010, 4 p.m.
Remaining Early StartOct. 5, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDtPa4FjUjc0mRsHQNYdYaaQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishDec. 3, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishDec. 3, 2010, 4 p.m. 
Late FinishJan. 13, 2011, noon 
Remaining Late FinishJan. 13, 2011, noon 
Remaining Late StartNov. 12, 2010, noon 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
352.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1744960.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1746410.0 PR_FS