1
General Informations
Project752
Global Unique IDDH6OMRtdkUiHCuV2UGkxSw
Unique ID174588
Activity NameProcess D/Sheet for Electric Heater
Added DateAug. 14, 2009, 1:50 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS37412
Total Float488.833333
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration176.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 3, 2009, 8:53 a.m.
Planned StartJan. 29, 2010, 8 a.m.
Actual StartNone
Activity IDHEK00PR060
Early StartJan. 29, 2010, 8 a.m.
Late StartApril 26, 2010, 8:50 a.m.
Remaining Early FinishMarch 1, 2010, 4 p.m.
Remaining Early StartJan. 29, 2010, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishMarch 1, 2010, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishMarch 1, 2010, 4 p.m. 
Late FinishMay 26, 2010, 8:50 a.m. 
Remaining Late FinishMay 26, 2010, 8:50 a.m. 
Remaining Late StartApril 26, 2010, 8:50 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
176.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1734580.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
17112380.0 PR_SS
Back