| General Informations | |
| Project | 22726 |
| Global Unique ID | vU/zl9/3RySXsGzYHybwWw |
| Unique ID | 2907334 |
| Activity Name | Engineering - Demin Water System Piping |
| Added Date | 25 novembre 2013 14:41 |
| Added By | admin |
| Activity Status | TK_NotStart |
| WBS | 307498 |
| Total Float | 592,0 |
| Activity Location | None |
| Est Weight | 1,0 |
| Phys Complete Pct | 0,0 |
| Calendar | 19658 |
| Percent Complete Type | CP_Drtn |
| Auto Compute Actuals | N |
| Remaining Duration | 920,0 |
| Primary Constraint | None |
| Secondary Constraint | None |
| Primary Constraint Date | None |
| Secondary Constraint Date | None |
| Primary Resource | None |
| Actual Nonlabor Units | 0,0 |
| Actual This Period Nonlabor Units | 0,0 |
| Actual This Period Labor Units | 0,0 |
| Actual Labor Units | 0,0 |
| Planned Labor Units Budgeted or Planned Labor Units | 0,0 |
| Remaining Nonlabor Units | 0,0 |
| Remaining Labor Units | 0,0 |
| Planned Nonlabor Units Budgeted or Planned Nonlabor Units | 0,0 |
| Last Modified Date | 25 novembre 2013 14:41 |
| Planned Start | 7 mai 2014 08:00 |
| Actual Start | None |
| Activity ID | J4810 |
| Early Start | 7 mai 2014 08:00 |
| Late Start | 20 juillet 2014 08:00 |
| Remaining Early Finish | 29 août 2014 16:00 |
| Remaining Early Start | 7 mai 2014 08:00 |
| External Early Start | None |
| Expected Finish | None |
| Resume Date | None |
| New Feedback | N |
| Review Status | |
| Activity Leveling Priority | PT_Normal |
| Methodology Global Unique ID | ruLeNJhSJkmRwqI/52D1pg |
| Lock Remaining | N |
| Last Modified By | admin | |
| Planned Finish | 29 août 2014 16:00 | |
| Actual Finish | None | |
| Activity Type | TT_Task | |
| Early Finish | 29 août 2014 16:00 | |
| Late Finish | 11 novembre 2014 16:00 | |
| Remaining Late Finish | 11 novembre 2014 16:00 | |
| Remaining Late Start | 20 juillet 2014 08:00 | |
| External Late Finish | None | |
| Review Finish | ||
| Suspend Date | None | |
| Longest Path | N | |
| Free Float | 0,0 | |
| Float Path | ||
| Float Path Order | ||
| Duration Type | DT_FixedDUR2 | |
| Planned Duration Original or Planned Duration | 920,0 |
| Task Id | Lag (day) | Succ Type | |
| 2907315 | 56,0 | PR_SS |
| Task Id | Lag (day) | Succ Type | |
| 2908246 | -560,0 | PR_FS |