Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDqcpPui43YkCs+v6g9oHLYg
Unique ID172580
Activity NamePainting Materials: Issue PO to Vendor
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37490
Total Float320,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date11 septembre 2009 14:56
Planned Start26 août 2010 08:00
Actual StartNone
Activity IDHPP03PI030
Early Start26 août 2010 08:00
Late Start21 octobre 2010 08:00
Remaining Early Finish3 septembre 2010 16:00
Remaining Early Start26 août 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDeEAoRMlBgE2gQfdBRcgTNg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish3 septembre 2010 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish3 septembre 2010 16:00 
Late Finish29 octobre 2010 16:00 
Remaining Late Finish29 octobre 2010 16:00 
Remaining Late Start21 octobre 2010 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725790,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728630,0 PR_FS