Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDpSJyOqAzm0ixfO812joOVQ
Unique ID172583
Activity NameInsulation Materials: Issue PO to Vendor
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37490
Total Float389,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start20 octobre 2010 08:00
Actual StartNone
Activity IDHPP03PI060
Early Start20 octobre 2010 08:00
Late Start27 décembre 2010 13:00
Remaining Early Finish28 octobre 2010 16:00
Remaining Early Start20 octobre 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDvY9O78IFUUWyDFjLkQsWRw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish28 octobre 2010 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish28 octobre 2010 16:00 
Late Finish5 janvier 2011 13:00 
Remaining Late Finish5 janvier 2011 13:00 
Remaining Late Start27 décembre 2010 13:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float8,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725820,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728650,0 PR_FS
Back