Activity NamePiping Bulk Material: 1st Delivery at Site
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37399
Total Float987,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration253,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start4 septembre 2010 08:00
Actual StartNone
Activity IDMKP03PP020
Early Start4 septembre 2010 08:00
Late Start25 janvier 2011 11:00
Remaining Early Finish10 octobre 2010 13:00
Remaining Early Start4 septembre 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDY4SXN99zkkuBAQHIZM4SWg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish10 octobre 2010 13:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish10 octobre 2010 13:00 
Late Finish2 mars 2011 16:00 
Remaining Late Finish2 mars 2011 16:00 
Remaining Late Start25 janvier 2011 11:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
253,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
172851400,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1714270,0 PR_FS
1735420,0 PR_FS
Back