Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID47WLTyWCEUCRxQXHGyTlHQ
Unique ID172854
Activity NameHV/MV/LV Cables: Delivery at Site
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37383
Total Float278,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration448,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start19 avril 2011 10:00
Actual StartNone
Activity IDMKP03EL080
Early Start19 avril 2011 10:00
Late Start30 mai 2011 08:00
Remaining Early Finish23 juin 2011 10:00
Remaining Early Start19 avril 2011 10:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDUT8gauNPjUSRJ2llQweSUg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish23 juin 2011 10:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish23 juin 2011 10:00 
Late Finish2 août 2011 16:00 
Remaining Late Finish2 août 2011 16:00 
Remaining Late Start30 mai 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float54,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
448,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1728530,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1735480,0 PR_FS