Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID5gS4QZd48EWzEJmYxtkvPQ
Unique ID172862
Activity NameInstrument Bulk: Delivery at Site
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37384
Total Float216,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration352,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start13 août 2011 08:00
Actual StartNone
Activity IDMKP03IC020
Early Start13 août 2011 08:00
Late Start13 septembre 2011 08:00
Remaining Early Finish2 octobre 2011 16:00
Remaining Early Start13 août 2011 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDEhuyD3esMkWEpDUc1flNMg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish2 octobre 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish2 octobre 2011 16:00 
Late Finish2 novembre 2011 16:00 
Remaining Late Finish2 novembre 2011 16:00 
Remaining Late Start13 septembre 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float5,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
352,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1728610,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1714280,0 PR_FS
1735500,0 PR_FS
Back