Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDAEyCLiqMz0eDAzcIG2aeTQ
Unique ID172869
Activity NameFireproofing Materials: Manufacturing / Fabrication
Added Date4 août 2009 08:36
Added Byadmin
Activity StatusTK_NotStart
WBS37386
Total Float573,333333
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration744,5
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date3 novembre 2009 08:53
Planned Start5 janvier 2011 15:30
Actual StartNone
Activity IDMKP03FS010
Early Start5 janvier 2011 15:30
Late Start30 mars 2011 12:50
Remaining Early Finish24 avril 2011 16:00
Remaining Early Start5 janvier 2011 15:30
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDkBoTgQ31dk6gEX2VwxqNkg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish24 avril 2011 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish24 avril 2011 16:00 
Late Finish17 juillet 2011 13:20 
Remaining Late Finish17 juillet 2011 13:20 
Remaining Late Start30 mars 2011 12:50 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
744,5 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1725950,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1728700,0 PR_FS
Back