Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDpp3Agae9rkafoIQwvRvw9Q
Unique ID173972
Activity NameTank Hydrotest
Added Date10 août 2009 09:26
Added Byadmin
Activity StatusTK_NotStart
WBS38667
Total Float312,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration424,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start2 juin 2012 08:00
Actual StartNone
Activity IDCCF23TK020
Early Start2 juin 2012 08:00
Late Start17 juillet 2012 08:00
Remaining Early Finish1 août 2012 16:00
Remaining Early Start2 juin 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDQV8idU87AE6P9Uzaloketg
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish1 août 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish1 août 2012 16:00 
Late Finish16 septembre 2012 16:00 
Remaining Late Finish16 septembre 2012 16:00 
Remaining Late Start17 juillet 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
424,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1739760,0 PR_FS
1739730,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1739740,0 PR_FS
Back