Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDNLPptIAx2kqKXqSH9MZ+dg
Unique ID173980
Activity NameTank Painting / Lining Works
Added Date10 août 2009 09:28
Added Byadmin
Activity StatusTK_NotStart
WBS38674
Total Float192,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration576,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start2 septembre 2012 08:00
Actual StartNone
Activity IDCCF24PI010
Early Start2 septembre 2012 08:00
Late Start30 septembre 2012 08:00
Remaining Early Finish24 novembre 2012 16:00
Remaining Early Start2 septembre 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDoTRUmVCkx06nbPsjBWYk6Q
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish24 novembre 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish24 novembre 2012 16:00 
Late Finish22 décembre 2012 16:00 
Remaining Late Finish22 décembre 2012 16:00 
Remaining Late Start30 septembre 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
576,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1739780,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1739810,0 PR_FS
Back