Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDKSvhsviXskeI3QTYd0VvFw
Unique ID174033
Activity NameIn-tank Equipment Erection
Added Date10 août 2009 11:11
Added Byadmin
Activity StatusTK_NotStart
WBS38708
Total Float304,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration304,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start3 juin 2012 08:00
Actual StartNone
Activity IDCCF54ME010
Early Start3 juin 2012 08:00
Late Start17 juillet 2012 08:00
Remaining Early Finish16 juillet 2012 16:00
Remaining Early Start3 juin 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDFuokcjnBQUaAkyqV48G51g
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish16 juillet 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish16 juillet 2012 16:00 
Late Finish29 août 2012 16:00 
Remaining Late Finish29 août 2012 16:00 
Remaining Late Start17 juillet 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float112,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
304,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1740361256,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1740320,0 PR_FS
Back