Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID1yZveSaSekikqb2ZJWyFfQ
Unique ID174501
Activity NameInstu. wiring Layout Dwgs- FC
Added Date13 août 2009 10:48
Added Byadmin
Activity StatusTK_NotStart
WBS37446
Total Float723,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration701,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start27 octobre 2010 08:00
Actual StartNone
Activity IDHEK00IC090
Early Start27 octobre 2010 08:00
Late Start2 mars 2011 11:00
Remaining Early Finish25 février 2011 13:00
Remaining Early Start27 octobre 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID+XTdnsS1jE2smqMcB7nQlQ
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish25 février 2011 13:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish25 février 2011 13:00 
Late Finish1 juillet 2011 16:00 
Remaining Late Finish1 juillet 2011 16:00 
Remaining Late Start2 mars 2011 11:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float723,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
701,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
174500160,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1735520,0 PR_FS
174400600,0 PR_FS
Back