Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique ID1dHAWlBbfEuWk4URqf7vAw
Unique ID174670
Activity NameTank Plates - Neptha/Gasoil: Issue PO
Added Date25 août 2009 09:19
Added Byadmin
Activity StatusTK_NotStart
WBS37496
Total Float224,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar864
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration56,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start10 mai 2010 08:00
Actual StartNone
Activity IDHPP02TO040
Early Start10 mai 2010 08:00
Late Start17 juin 2010 08:00
Remaining Early Finish18 mai 2010 16:00
Remaining Early Start10 mai 2010 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDV3H2VxV9VEWZqHUtAbgmnw
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish18 mai 2010 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish18 mai 2010 16:00 
Late Finish25 juin 2010 16:00 
Remaining Late Finish25 juin 2010 16:00 
Remaining Late Start17 juin 2010 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
56,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1726130,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1746710,0 PR_SS
1711030,0 PR_FS
1728410,0 PR_FS
Back