1
General Informations
Project752
Global Unique IDtvcXAVMnCkiZPCPoRhyE2Q
Unique ID174719
Activity NameTank Pneumatic test
Added Date25 août 2009 14:41
Added Byadmin
Activity StatusTK_NotStart
WBS39015
Total Float144,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration24,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 16:04
Planned Start8 septembre 2012 08:00
Actual StartNone
Activity IDCCF66TK110
Early Start8 septembre 2012 08:00
Late Start29 septembre 2012 08:00
Remaining Early Finish10 septembre 2012 16:00
Remaining Early Start8 septembre 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDg5a0OnVoSUuL1UL05fvt8g
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish10 septembre 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish10 septembre 2012 16:00 
Late Finish1 octobre 2012 16:00 
Remaining Late Finish1 octobre 2012 16:00 
Remaining Late Start29 septembre 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
24,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1747140,0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
1747200,0 PR_FS