| General Informations | |
| Project | 752 |
| Global Unique ID | vvnxsy0kwESx+WSz07QhMQ |
| Unique ID | 174994 |
| Activity Name | F44: Commissioning |
| Added Date | 2 septembre 2009 10:17 |
| Added By | admin |
| Activity Status | TK_NotStart |
| WBS | 39051 |
| Total Float | 136,0 |
| Activity Location | None |
| Est Weight | 1,0 |
| Phys Complete Pct | 0,0 |
| Calendar | 866 |
| Percent Complete Type | CP_Drtn |
| Auto Compute Actuals | N |
| Remaining Duration | 240,0 |
| Primary Constraint | None |
| Secondary Constraint | None |
| Primary Constraint Date | None |
| Secondary Constraint Date | None |
| Primary Resource | None |
| Actual Nonlabor Units | 0,0 |
| Actual This Period Nonlabor Units | 0,0 |
| Actual This Period Labor Units | 0,0 |
| Actual Labor Units | 0,0 |
| Planned Labor Units Budgeted or Planned Labor Units | 0,0 |
| Remaining Nonlabor Units | 0,0 |
| Remaining Labor Units | 0,0 |
| Planned Nonlabor Units Budgeted or Planned Nonlabor Units | 0,0 |
| Last Modified Date | 30 octobre 2009 15:31 |
| Planned Start | 8 décembre 2012 08:00 |
| Actual Start | None |
| Activity ID | COA05KA180 |
| Early Start | 8 décembre 2012 08:00 |
| Late Start | 27 décembre 2012 08:00 |
| Remaining Early Finish | 10 janvier 2013 16:00 |
| Remaining Early Start | 8 décembre 2012 08:00 |
| External Early Start | None |
| Expected Finish | None |
| Resume Date | None |
| New Feedback | N |
| Review Status | |
| Activity Leveling Priority | PT_Normal |
| Methodology Global Unique ID | 2TNV7/AV9kCtJ0seTvoB4w |
| Lock Remaining | N |
| Last Modified By | admin | |
| Planned Finish | 10 janvier 2013 16:00 | |
| Actual Finish | None | |
| Activity Type | TT_Task | |
| Early Finish | 10 janvier 2013 16:00 | |
| Late Finish | 30 janvier 2013 16:00 | |
| Remaining Late Finish | 30 janvier 2013 16:00 | |
| Remaining Late Start | 27 décembre 2012 08:00 | |
| External Late Finish | None | |
| Review Finish | ||
| Suspend Date | None | |
| Longest Path | N | |
| Free Float | 136,0 | |
| Float Path | ||
| Float Path Order | ||
| Duration Type | DT_FixedDUR2 | |
| Planned Duration Original or Planned Duration | 240,0 |
| Task Id | Lag (day) | Succ Type | |
| 174234 | 1520,0 | PR_FS | |
| 175209 | 0,0 | PR_FS | |
| 175210 | 0,0 | PR_FS | |
| 175211 | 0,0 | PR_FS |
| Task Id | Lag (day) | Succ Type | |
| 175261 | 0,0 | PR_FS |