Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDGEmAvjW6xUKyncel55kM7w
Unique ID175122
Activity NameElectrical Equipment Installation
Added Date7 septembre 2009 09:38
Added Byadmin
Activity StatusTK_NotStart
WBS39084
Total Float80,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration2240,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start1 décembre 2011 08:00
Actual StartNone
Activity IDCCA02EE040
Early Start1 décembre 2011 08:00
Late Start13 décembre 2011 08:00
Remaining Early Finish22 octobre 2012 16:00
Remaining Early Start1 décembre 2011 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDjVr8+nFcxU+iLcl2opG4gQ
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish22 octobre 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish22 octobre 2012 16:00 
Late Finish3 novembre 2012 16:00 
Remaining Late Finish3 novembre 2012 16:00 
Remaining Late Start13 décembre 2011 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float64,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
2240,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1751180,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1751290,0 PR_FF
Back